Renovations run from August to November 2011.

Work is done from 7 a.m. to 5 p.m. on weekdays.

The project begins the week of August 1, beginning at the intersection of South and New Pruyn Streets near Hudson Avenue. Work progresses toward the intersection of South and Glen Streets.

Work commences on the south side of South Street, beginning at New Pruyn Street. In September, when work is completed on the south side, it will switch over to the north side of South Street at the intersection of South and Broad Streets by Rite Aid and Union Square.

  • Week of August 1
    • South side of South Street
    • Beginning at the intersection of South and New Pruyn Streets near Hudson Avenue and continuing for the next 4 to 5 weeks, work crews will be removing existing storm drainage lines and replacing with new lines, installing new water line and replacing existing manhole covers. Sewer lines will be repaired where necessary and existing sidewalks will be removed and replaced. Work will progress on this side of the street all the way to Glen Street.
  • Week of September 9
    • North side of South Street
    • For the next 4 to 5 weeks, work will shift to the north side of the street, commencing by the intersection of South and Broad streets by Rite Aid and the Union Square Complex and it will progress toward Glen Street, replacing curbs and sidewalks and installing new trees, replacing some existing trees.
  • Mid-October
    • For 3 to 4 weeks, street lighting, streetscaping, park benches, landscaping, tree planting and paving will be underway.
  • End of November
    • Project completion